Cost to Build an Assisted Living Facility in Idaho: 2026 Construction Guide
Building an assisted living facility in Idaho offers attractive economics compared to coastal markets, with moderate construction costs and strong demographic demand. Understanding the full scope of development costs is essential for successful project planning and financing in the Gem State.
Planning to Build an Idaho ALF?
Get expert construction financing guidance from Jaken Finance Group.
Get Your Free Construction Quote →Idaho Construction Cost Overview
Regional Cost Comparison
| Cost Component | Boise Metro | Coeur d'Alene | Idaho Falls | Twin Falls |
|---|---|---|---|---|
| Land (per acre) | $400K-1M | $300K-800K | $150K-400K | $100K-300K |
| Hard Costs (per SF) | $220-300 | $230-310 | $200-275 | $190-260 |
| Soft Costs (% of hard) | 13-17% | 14-18% | 12-15% | 12-15% |
| FF&E (per bed) | $10-15K | $10-15K | $9-14K | $9-13K |
| Total per Bed | $230-280K | $240-300K | $200-250K | $190-240K |
Idaho vs. National Averages
| Metric | Idaho | National Average | Difference |
|---|---|---|---|
| Hard Costs/SF | $220-280 | $275-350 | -15-20% |
| Land Costs | Moderate | High | -20-40% |
| Labor Costs | Below average | Average | -10-15% |
| Total Project Cost | $200-260K/bed | $250-350K/bed | -15-25% |
Land Costs
Regional Land Prices
Boise Metropolitan Area:
| Location | Price per Acre | Availability |
|---|---|---|
| Downtown Boise | $800K-1.5M | Very Limited |
| Meridian | $500K-900K | Limited |
| Nampa | $350K-600K | Moderate |
| Eagle | $600K-1M | Limited |
| Caldwell | $250K-450K | Good |
North Idaho:
| Location | Price per Acre | Availability |
|---|---|---|
| Coeur d'Alene | $400K-800K | Limited |
| Post Falls | $300K-600K | Moderate |
| Hayden | $350K-700K | Limited |
| Sandpoint | $300K-600K | Moderate |
Eastern Idaho:
| Location | Price per Acre | Availability |
|---|---|---|
| Idaho Falls | $200K-400K | Good |
| Pocatello | $150K-300K | Good |
| Rexburg | $175K-350K | Moderate |
| Twin Falls | $150K-300K | Good |
Land Requirements
Typical Site Needs:
- 60-bed facility: 2.5-4 acres
- 80-bed facility: 3.5-5 acres
- 100-bed facility: 4.5-6 acres
Site Considerations:
- Zoning compatibility
- Utility availability
- Access and visibility
- Topography
- Environmental factors
- Future expansion potential
Hard Construction Costs
Building Cost Breakdown
Per Square Foot Costs (2026):
| Component | Boise | Coeur d'Alene | Idaho Falls | Twin Falls |
|---|---|---|---|---|
| Site Work | $15-25 | $18-28 | $12-20 | $12-18 |
| Foundation | $18-25 | $20-28 | $16-22 | $15-20 |
| Structure | $45-60 | $48-65 | $42-55 | $40-52 |
| Exterior | $25-35 | $28-38 | $22-30 | $20-28 |
| Roofing | $12-18 | $14-20 | $10-15 | $10-14 |
| Interior Finishes | $55-75 | $58-80 | $50-68 | $48-65 |
| MEP Systems | $50-65 | $52-68 | $48-60 | $45-58 |
| Specialties | $10-15 | $12-18 | $8-12 | $8-12 |
| Total | $230-318 | $250-345 | $208-282 | $198-267 |
Building Size Guidelines
Typical Square Footage:
| Facility Size | Total SF | SF per Bed |
|---|---|---|
| 40 beds | 28,000-36,000 | 700-900 |
| 60 beds | 42,000-54,000 | 700-900 |
| 80 beds | 56,000-72,000 | 700-900 |
| 100 beds | 70,000-90,000 | 700-900 |
Construction Type Impact
| Construction Type | Cost/SF | Pros | Cons |
|---|---|---|---|
| Wood Frame | $200-260 | Lower cost, faster | Height limits, fire concerns |
| Steel Frame | $240-300 | Durability, flexibility | Higher cost |
| Concrete | $260-320 | Fire resistance, longevity | Highest cost, longer timeline |
Soft Costs
Soft Cost Categories
| Category | % of Hard Costs | Typical Range |
|---|---|---|
| Architecture/Engineering | 5-7% | $400K-700K |
| Permits and Fees | 1-2% | $80K-200K |
| Legal | 0.5-1% | $40K-100K |
| Accounting | 0.3-0.5% | $25K-50K |
| Market Study | 0.1-0.2% | $15K-25K |
| Appraisal | 0.1-0.2% | $15K-30K |
| Environmental | 0.1-0.2% | $10K-25K |
| Surveys | 0.1-0.2% | $10K-25K |
| Insurance | 0.5-1% | $40K-100K |
| Financing Costs | 2-3% | $160K-300K |
| Developer Fee | 3-5% | $240K-500K |
| Total Soft Costs | 13-18% | $1.0M-2.0M |
Permitting Costs by Region
| Jurisdiction | Building Permit | Impact Fees | Other Fees |
|---|---|---|---|
| Boise | $25K-50K | $50K-150K | $15K-30K |
| Meridian | $20K-45K | $40K-120K | $12K-25K |
| Coeur d'Alene | $18K-40K | $30K-80K | $10K-20K |
| Idaho Falls | $15K-35K | $20K-60K | $8K-18K |
| Twin Falls | $12K-30K | $15K-45K | $6K-15K |
FF&E Costs
Furniture, Fixtures & Equipment
Per Bed Budgets:
| Category | Budget | Mid-Range | Premium |
|---|---|---|---|
| Resident Room | $4,000-5,500 | $5,500-7,500 | $7,500-10,000 |
| Common Areas | $2,000-3,000 | $3,000-4,500 | $4,500-6,000 |
| Dining | $1,500-2,500 | $2,500-3,500 | $3,500-5,000 |
| Kitchen | $1,000-1,500 | $1,500-2,500 | $2,500-4,000 |
| Administrative | $500-1,000 | $1,000-1,500 | $1,500-2,500 |
| Total per Bed | $9,000-13,500 | $13,500-19,500 | $19,500-27,500 |
Technology Investments
| System | Cost Range | Notes |
|---|---|---|
| Nurse Call System | $50K-100K | Required |
| Security/Access | $30K-60K | Cameras, access control |
| Fire Alarm | $40K-80K | Code required |
| Phone/Data | $25K-50K | Infrastructure |
| EHR System | $20K-50K | Software and setup |
| Entertainment | $15K-30K | TVs, common areas |
| Total Technology | $180K-370K |
Sample Project Budgets
60-Bed Facility - Boise Metro
| Category | Cost | % of Total |
|---|---|---|
| Land (3 acres) | $1,800,000 | 11% |
| Hard Construction (48,000 SF) | $12,000,000 | 72% |
| Soft Costs | $1,800,000 | 11% |
| FF&E | $720,000 | 4% |
| Working Capital | $350,000 | 2% |
| Total | $16,670,000 | 100% |
| Cost per Bed | $277,833 |
60-Bed Facility - Idaho Falls
| Category | Cost | % of Total |
|---|---|---|
| Land (3 acres) | $750,000 | 6% |
| Hard Construction (48,000 SF) | $10,560,000 | 76% |
| Soft Costs | $1,400,000 | 10% |
| FF&E | $660,000 | 5% |
| Working Capital | $300,000 | 2% |
| Total | $13,670,000 | 100% |
| Cost per Bed | $227,833 |
80-Bed Facility - Coeur d'Alene
| Category | Cost | % of Total |
|---|---|---|
| Land (4 acres) | $2,400,000 | 11% |
| Hard Construction (64,000 SF) | $17,280,000 | 75% |
| Soft Costs | $2,600,000 | 11% |
| FF&E | $1,040,000 | 5% |
| Working Capital | $450,000 | 2% |
| Total | $23,770,000 | 100% |
| Cost per Bed | $297,125 |
Cost Factors and Variables
Cost Drivers
Increasing Costs:
- Labor shortages
- Material price inflation
- Land appreciation (Boise)
- Regulatory requirements
- Quality expectations
- Technology requirements
Cost Reduction Opportunities:
- Value engineering
- Efficient design
- Competitive bidding
- Phased development
- Alternative locations
- Standardized plans
Regional Considerations
Boise Metro:
- Highest land costs
- Most competitive labor market
- Fastest permitting (generally)
- Best contractor availability
- Premium market supports costs
North Idaho:
- Seasonal construction challenges
- Limited contractor pool
- Higher material transport costs
- Premium market positioning
- Scenic site premiums
Eastern/Southern Idaho:
- Lower overall costs
- Good contractor availability
- Longer permitting in some areas
- Lower market rates
- Value-focused development
Financing Construction Costs
Construction Loan Options
| Loan Type | LTC | Rate | Term |
|---|---|---|---|
| Bank Construction | 70-80% | Prime + 1-2% | 18-24 months |
| SBA 504 | 90% | Fixed + Variable | Construction + Perm |
| HUD 232 | 85% | Fixed | 40 years |
Equity Requirements
Typical Equity Needs:
| Loan Type | Equity Required | 60-Bed Project |
|---|---|---|
| Bank | 20-30% | $3.3M-5.0M |
| SBA | 10-15% | $1.7M-2.5M |
| HUD | 15-20% | $2.5M-3.3M |
Timeline and Phasing
Development Timeline
| Phase | Duration | Key Activities |
|---|---|---|
| Pre-Development | 6-12 months | Site selection, design, approvals |
| Financing | 2-4 months | Loan application, closing |
| Construction | 12-18 months | Building construction |
| Lease-Up | 12-18 months | Marketing, occupancy ramp |
| Total | 32-52 months |
Idaho-Specific Timeline Factors
Advantages:
- Generally efficient permitting
- Business-friendly environment
- Available contractors
- Reasonable inspection timelines
Challenges:
- Winter construction limitations
- Seasonal labor availability
- Material delivery to rural areas
- DHW licensing timeline
Cost Management Strategies
Pre-Construction
- Thorough Planning: Complete design before bidding
- Value Engineering: Optimize design for cost
- Competitive Bidding: Multiple contractor bids
- Fixed-Price Contracts: Lock in costs where possible
- Contingency Planning: Adequate reserves
During Construction
- Change Order Control: Minimize scope changes
- Progress Monitoring: Regular site visits
- Draw Management: Verify work before payment
- Quality Control: Prevent costly rework
- Timeline Management: Avoid delay costs
Related Resources
Idaho-Specific Pages
- Idaho ALF Construction Loans
- Idaho ALF Regulations
- Idaho ALF Market Trends 2026
- Apply for Idaho ALF Financing
General Resources
Ready to Build Your Idaho Assisted Living Facility?
Jaken Finance Group specializes in construction financing for assisted living facilities throughout Idaho. Get expert guidance on your development project.
Get Your Free Construction Quote →Disclaimer: Construction costs vary significantly based on location, design, market conditions, and timing. These estimates are for planning purposes only. Obtain detailed bids from qualified contractors for accurate project budgeting. All financing provided by Jaken Finance Group, subject to approval.