Cost to Build an Assisted Living Facility in Georgia

Building an assisted living facility in Georgia requires significant capital investment, with costs varying based on location, size, and amenity level. This comprehensive guide provides detailed cost estimates for ALF construction across the Peach State, from Atlanta's premium markets to more affordable secondary locations.

Finance Your Georgia ALF Construction Project

Jaken Finance Group specializes in construction financing for Georgia assisted living facilities.

Get Your Construction Loan Quote →

Georgia ALF Construction Cost Overview

Cost Per Bed Summary by Region

Region Cost Per Bed Cost Per Unit Total Project (60-bed)
Atlanta Metro $140,000-$200,000 $175,000-$250,000 $10-14 million
North Atlanta Suburbs $160,000-$230,000 $200,000-$290,000 $12-17 million
Savannah/Coastal $120,000-$170,000 $150,000-$210,000 $9-12 million
Augusta $110,000-$160,000 $140,000-$200,000 $8-11 million
Macon/Columbus $100,000-$150,000 $125,000-$185,000 $7-10 million
Rural Georgia $90,000-$140,000 $115,000-$175,000 $6-9 million

Costs as of 2026, subject to market conditions

Key Cost Drivers

  1. Land costs - Varies dramatically by location
  2. Labor rates - Regional differences across Georgia
  3. Building type - Wood frame vs. steel/concrete
  4. Amenity level - Basic vs. luxury finishes
  5. Memory care - Specialized design requirements
  6. Site conditions - Grading, utilities, environmental

Detailed Cost Breakdown

Land Acquisition Costs

Location Cost Per Acre Typical Site Size Land Cost
North Atlanta (Alpharetta, Roswell) $800,000-$1.5M 3-4 acres $2.4-6 million
Atlanta Metro $500,000-$1M 3-4 acres $1.5-4 million
Savannah $300,000-$600,000 3-4 acres $900K-2.4 million
Augusta $200,000-$400,000 3-5 acres $600K-2 million
Macon/Columbus $150,000-$350,000 3-5 acres $450K-1.75 million
Rural Georgia $75,000-$200,000 4-6 acres $300K-1.2 million

Hard Construction Costs

Building Shell and Structure:

Component Cost Per SF Notes
Foundation $10-18 Varies by soil conditions
Structural frame $20-35 Wood frame to steel
Exterior envelope $22-38 Brick, EIFS, or combination
Roofing $9-16 Pitched or flat
Windows/doors $10-20 Commercial grade
Subtotal $71-127/SF

Interior Construction:

Component Cost Per SF Notes
Interior partitions $9-16 Drywall, sound insulation
Flooring $6-14 LVT, carpet, tile
Ceilings $5-9 Acoustic tile, drywall
Millwork/casework $7-14 Cabinets, trim
Painting/finishes $4-7 Standard to premium
Subtotal $31-60/SF

Mechanical, Electrical, Plumbing (MEP):

System Cost Per SF Notes
HVAC $20-32 Individual units preferred
Plumbing $14-22 High fixture count
Electrical $16-26 Emergency power, nurse call
Fire protection $6-11 Full sprinkler system
Low voltage $6-12 Security, communications
Subtotal $62-103/SF

Get Accurate Construction Cost Estimates

Our team can help you develop realistic budgets for your Georgia ALF project.

Discuss Your Project →

Regional Construction Cost Analysis

Atlanta Metro Area

Market Characteristics:

Sample Budget - 60-Bed Atlanta Suburban ALF:

Category Cost % of Total
Land (3 acres) $2,100,000 16%
Hard costs (45,000 SF @ $220/SF) $9,900,000 65%
Soft costs $1,485,000 10%
FF&E $675,000 4%
Contingency (5%) $495,000 3%
Total $14,655,000 100%
Cost per bed $244,000

North Atlanta Suburbs (Alpharetta, Roswell, Johns Creek)

Market Characteristics:

Sample Budget - 60-Bed North Atlanta Premium ALF:

Category Cost % of Total
Land (3 acres) $3,000,000 18%
Hard costs (45,000 SF @ $250/SF) $11,250,000 64%
Soft costs $1,687,500 10%
FF&E $800,000 5%
Contingency (5%) $562,500 3%
Total $17,300,000 100%
Cost per bed $288,000

Savannah/Coastal Georgia

Market Characteristics:

Sample Budget - 50-Bed Savannah Area ALF:

Category Cost % of Total
Land (3 acres) $900,000 10%
Hard costs (37,500 SF @ $195/SF) $7,312,500 71%
Soft costs $1,096,875 11%
FF&E $550,000 5%
Contingency (5%) $365,625 4%
Total $10,225,000 100%
Cost per bed $205,000

Secondary Markets (Augusta, Macon, Columbus)

Market Characteristics:

Sample Budget - 50-Bed Augusta Area ALF:

Category Cost % of Total
Land (4 acres) $600,000 7%
Hard costs (37,500 SF @ $175/SF) $6,562,500 72%
Soft costs $984,375 11%
FF&E $500,000 5%
Contingency (5%) $328,125 4%
Total $8,975,000 100%
Cost per bed $180,000

Soft Costs Breakdown

Pre-Development Costs

Item Typical Cost Notes
Feasibility study $10,000-$25,000 Market and financial analysis
Environmental (Phase I) $2,000-$4,000 Required for financing
Geotechnical study $5,000-$10,000 Soil analysis
Survey $4,000-$10,000 Boundary and topographic
Zoning/entitlements $5,000-$30,000 Varies by municipality

Design and Engineering

Item Typical Cost Notes
Architectural design 5-8% of hard costs Full design services
Structural engineering 0.5-1% of hard costs Included or separate
MEP engineering 1-2% of hard costs Mechanical, electrical, plumbing
Civil engineering $20,000-$50,000 Site design
Interior design $35,000-$100,000 Finishes and furnishings
Landscape design $10,000-$30,000 Site landscaping

Permits and Fees

Item Typical Cost Notes
Building permit 0.75-1.5% of construction Municipality-specific
Plan review fees $6,000-$20,000 Multiple reviews
Impact fees $20,000-$100,000 Varies significantly
Utility connection $30,000-$100,000 Water, sewer, electric
DCH fees $600-$1,500 Licensing fees

Professional Services

Item Typical Cost Notes
Legal fees $20,000-$50,000 Entity formation, contracts
Accounting $10,000-$20,000 Project accounting
Construction management 3-5% of hard costs If used
Lender inspections $10,000-$20,000 During construction
Appraisal $5,000-$10,000 Required for financing

FF&E and Equipment Costs

Furniture, Fixtures & Equipment

Category Cost Per Bed Notes
Resident room furniture $3,000-$6,000 Bed, dresser, seating
Common area furniture $1,500-$3,000 Allocated per bed
Dining furniture $1,000-$2,200 Tables, chairs
Activity/therapy equipment $350-$1,000 Recreation items
Total FF&E $5,850-$12,200

Specialized Equipment

Item Typical Cost Notes
Commercial kitchen $100,000-$250,000 Full service kitchen
Laundry equipment $20,000-$50,000 Commercial washers/dryers
Nurse call system $30,000-$75,000 Wired or wireless
Security system $18,000-$50,000 Cameras, access control
Emergency generator $50,000-$140,000 Life safety backup
Medical equipment $12,000-$35,000 Basic medical supplies

Memory Care Premium Costs

Additional Memory Care Requirements

Memory care units add 15-25% to base construction costs:

Feature Additional Cost Notes
Secured perimeter $35,000-$100,000 Doors, alarms, fencing
Wandering management $20,000-$55,000 Technology systems
Enhanced lighting $12,000-$35,000 Circadian rhythm support
Specialized flooring $10,000-$30,000 Non-glare, safe surfaces
Sensory features $18,000-$50,000 Gardens, activity spaces
Total Premium $95,000-$270,000 For 20-bed unit

Cost Management Strategies

Value Engineering Options

  1. Building design - Efficient floor plans reduce SF per bed
  2. Material selection - Durable but cost-effective finishes
  3. Phased construction - Build in stages as demand grows
  4. Standardization - Repeat room designs reduce costs
  5. Local sourcing - Reduce transportation costs

Contingency Planning

Recommended Contingencies:

Project Phase Contingency % Notes
Pre-construction 10-15% Design development
Construction 5-10% Unforeseen conditions
FF&E 5% Price fluctuations
Overall 7-10% Total project

Financing Your Georgia ALF Construction

Construction Loan Options

Loan Type Down Payment Term Best For
SBA 504 10-15% 20-25 years Owner-operators
HUD 232 15% 40 years Large projects
Conventional 20-30% 3-5 years Experienced developers
Bridge 25-35% 1-3 years Quick starts

Related Georgia ALF Resources


Get Financing for Your Georgia ALF Project

Jaken Finance Group provides construction financing tailored to Georgia assisted living development.

Get Your Construction Loan Quote →

Disclaimer: Construction costs vary significantly based on project specifics, market conditions, and timing. These estimates are for planning purposes only. Consult with qualified contractors and construction professionals for accurate project budgets. All financing provided by Jaken Finance Group, subject to approval.